Production begins from Egypt’s Atoll gas field seven months ahead of schedule: BP

Production from Atoll is now at 350 million cubic feet of gas per day, in addition to 10,000 barrels of condensate per day

Ahram Online , Monday 12 Feb 2018
Atoll gas field
BP announced that production officially began from Atoll gas field at a capacity of 350 million cubic feet per day. (Photo courtesy of BP official website)
Share/Bookmark
Views: 3666
Share/Bookmark
Views: 3666

Production from Egypt’s offshore gas field Atoll has started seven months ahead of schedule, BP announced in a press release on Monday.

The company also announced savings in expenditure, with the Atoll Phase One project being delivered 33 percent below the initial cost estimate.

“The longstanding partnerships we have in Egypt allowed us to fast-track Atoll’s development and deliver first gas only 33 months after discovery,” said Bob Dudley, BP group chief executive.

“This is a further demonstration of our commitment to help realise Egypt’s oil and gas potential and meet the increasing demand from its growing population,” Dudley added.

Gas is now being produced from the field at 350 million cubic feet of gas per day (cfpd), in addition to the production of 10,000 barrels of condensate per day.

Production from the field, located in the North Damietta concession in the East Nile Delta, will feed into Egypt’s national gas grid.

Egypt’s natural gas production currently stands at 5.5 billion cfpd, Petroleum Minister Tarek El Molla said earlier this month.

Production is expected to reach 6 billion cfpd by year-end.

BP announced the discovery of Atoll gas field in March 2015.

The field’s main reservoir is estimated to hold 1.5 trillion cubic feet of gas and 31 million barrels of condensates.

“The Atoll Phase One project is an early production scheme involving almost $1 billion investment,” the BP press release read.

“Atoll is our first major project in Egypt to be delivered in 2018, following the West Nile Delta Taurus and Libra project and then Zohr last year,” said Hesham Mekawi, Regional President, BP North Africa.

“We are extremely proud of Atoll’s efficient execution through our joint venture, the Pharaonic Petroleum Company,” Mekawi added.

Trial production from Atoll began in December at a production capacity of 300 million cubic feet per day of gas.

BP acquired a 10 percent stake in the Shorouk Concession from Eni last year; the concession contains the giant Zohr gas field, which began production in December.

Short link:

 

Email
 
Name
 
Comment's
Title
 
Comment
Ahram Online welcomes readers' comments on all issues covered by the site, along with any criticisms and/or corrections. Readers are asked to limit their feedback to a maximum of 1000 characters (roughly 200 words). All comments/criticisms will, however, be subject to the following code
  • We will not publish comments which contain rude or abusive language, libelous statements, slander and personal attacks against any person/s.
  • We will not publish comments which contain racist remarks or any kind of racial or religious incitement against any group of people, in Egypt or outside it.
  • We welcome criticism of our reports and articles but we will not publish personal attacks, slander or fabrications directed against our reporters and contributing writers.
  • We reserve the right to correct, when at all possible, obvious errors in spelling and grammar. However, due to time and staffing constraints such corrections will not be made across the board or on a regular basis.
Latest

© 2010 Ahram Online.